This is a mobile optimized page that loads fast, if you want to load the real page, click this text.

RXR - Robex Resources Inc.

Joined
27 June 2010
Posts
4,290
Reactions
360
Robex Resources is a gold mining company listed on the Toronto Stock Exchange – Venture ("TSX-V"), and is headquartered in Quebec, Canada.

Robex currently owns two assets in the highly prospective Birimian Greenstone belt: the Nampala producing gold mine in Mali, and the Kiniero Gold Project in Guinea (Conakry).

Robex is also active in exploration with drilling campaigns underway across its West African properties.

The Company intends to become a multi-mine, multi-jurisdiction gold producer in West Africa once the Kiniero Gold Project would be in production. Robex’s ambition is to continue to grow its asset base while committed to operating assets in an efficient, safe, responsible, and sustainable way.

It is anticipated that RX will list on the ASX on 6 june 2025.

 
Listing date06 June 2025 ; 1:00 PM AEST ##
Contact detailshttps://robexgold.com/
Ph: +1 581 741 7421
Principal ActivitiesThe Company’s main business undertaking is gold exploration, development and production. The Company’s key assets are located in the Birimian Greenstone Belt in West Africa: the Kiniero Project in Guinea and the operating Nampala Project in Mali.
Issue PriceAUD 3.11
Issue TypeCDIs
Security codeRXR
Capital to be Raised$120,000,000
Expected offer close date02 May 2025
UnderwriterEuroz Hartley's Ltd, Canaccord Genuity (Underwriters/Lead Managers), SCP Resources Finance LP (Co-Lead Manager), Blackwood Capital Pty Ltd (Co-Manager).
 
RXR has been listed for s month .... and trading ahead of the $3.11 IPO

Screenshot_20250703_201037_CommSec~2.jpg
.
Robex remains on track for first gold at Kiniero in Q4 2025
Highlights:
• Construction at Robex’s Kiniero Gold Project, Guinea, remains on schedule and budget with first gold pour on track for Q4 2025.
• Project remains LTI free (lost time injury).
• All project engineering and detail design completed.
• Phase 1 grade control drilling of Mansounia pit continues, with 55,430m drilled and 61,520 samples collected. Mansounia drilling to be completed by end of June, with drilling to commence at the Sabali pit.
• SMP (Structural, Mechanical & Piping) works commenced, with 115 tonnes erected in the milling building and pipe racks.
• All purchase orders for mechanical and electrical equipment, piping and electrical materials completed and on track for delivery, including 90% of power station materials collected and shipped.
• Process plant concrete is approximately 95% complete and power station concrete 32% complete.
• Structural steel and platework fabrication at 89% and 90% complete respectively, with 11 shipments of structural steel and four shipments of platework in transit to Kiniero. All fabrication is to be completed ahead of schedule.
• Field tank structures 64% completed. CIL Tank Train A is completed with CIL Tank Train B due for completion mid-July 2025.
• Preparation of Phase 1A of the tailings storage facility base is nearing completion, with 625,607m2 of 800,000m2 liner placed.
• Fuel supply contract was awarded and construction of the fuel storage facility commenced.
• Mill installation contract awarded, and the installation team is mobilising to site.
• Contracts for mining and drill and blast to be signed this month, with mobilisation commenced. ROM pad backfilling completed.
• Geotechnical drilling for a solar farm commenced.