Prelim Mining Study out. That's quick.
Initial cash costs look pretty high to me, and I am sure they will increase over time, as they always do. Under US$500 is OK I suppose.
Positive out of this is that it's on the previous resource and does not include any of the recent drilling or adding in what they come out with at Julie, which is good grade and shallow and will be able to be trucked to the Kunche/Bepkong Camp Mill.
No capital cost estimates for the 1m tn mill. That could come in at the operating surplus!
Need another decent discovery I feel, or they're looking marginal.
PRELIMINARY MINING STUDIES INDICATE ROBUST OPERATING MARGINS FOR WA GOLD PROJECT, GHANA
Mineral Resources Approaching Critical Mass for Development
Operating surplus of approximately A$138 million (US$112 million) generated from Kunche and Bepkong resources (1)
292,000oz of gold recoverable at cash cost of A$593/oz (US$483/oz)
Forecast production of 4.5 million tonnes at 2.24g/t gold
Low life-of-mine strip ratio of 4.2 : 1
Scoping Studies underway
Substantial drilling programme targeting additional gold resources to commence next month